2014年2月19日星期三

Microsoft 70-498 for the latest training materials

Microsoft 70-498 exam is very popular in IT field. Having 70-498 certificate is the best for those people who want to be promoted and is also a valid selection. And with the aid of 70-498 certification test, you can improve your skills and master some useful techniques in your job so that you can finish your work better and demonstrate your great ability before other people. Only in this way can you get more development opportunities.

Feedbacks of many IT professionals who have passed Microsoft certification 70-498 exam prove that their successes benefit from ITCertKing's help. ITCertKing's targeted test practice questions and answers to gave them great help, which save their valuable time and energy, and allow them to easily and smoothly pass their first Microsoft certification 70-498 exam. So ITCertKing a website worthy of your trust. Please select ITCertKing, you will be the next successful IT person. ITCertKing will help you achieve your dream.

If you use the ITCertKing Microsoft 70-498 study materials, you can reduce the time and economic costs of the exam. It can help you to pass the exam successfully. Before you decide to buy our Microsoft 70-498 exam materials, you can download our free test questions, including the PDF version and the software version. If you need software versions please do not hesitate to obtain a copy from our customer service staff.

Your dream is very high, so you have to find a lot of material to help you prepare for the exam. ITCertKing Microsoft 70-498 exam materials can help you to achieve your ideal. ITCertKing Microsoft 70-498 exam materials is a collection of experience and innovation from highly certified IT professionals in the field. Our products will let you try all the problems that may arise in a really examinations. We can give you a guarantee, to ensure that candidates get a 100% correct answer.

You can free download part of ITCertKing's exercises and answers about Microsoft certification 70-498 exam as a try, then you will be more confident to choose our ITCertKing's products to prepare your Microsoft certification 70-498 exam. Please add ITCertKing's products in you cart quickly.

Exam Code: 70-498
Exam Name: Microsoft (Delivering Continuous Value with Visual Studio 2012 Application Lifecycle Management)
One year free update, No help, Full refund!
Total Q&A: 75 Questions and Answers
Last Update: 2014-02-19

70-498 Free Demo Download: http://www.itcertking.com/70-498_exam.html

NO.1 You manage a development team that uses the Microsoft Visual Studio Scrum 2.0 process
template.
You establish a product backlog, allocate backlog items for a sprint, and define the tasks required to
complete the sprint. You need to ensure that the agreed upon work is assigned to team members.
Who should be responsible for assigning work to team members?
A. team members
B. product owner
C. team lead
D. scrum master
Answer: A

Microsoft   70-498 study guide   70-498 questions

NO.2 You manage several developers who are working on multiple applications. A business analyst
requests
an audit trail of work item changes for all prospective releases. You need to implement a strategy to
provide the audit trail.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose
two.)
A. Request that developers enter the work item ID in the check-in comments for any code changes
they
make.
B. Enable the automated build option to associate work items with the build.
C. Enable a check-in policy that requires a successful build prior to check-in.
D. Require developers to update the comments field of their tasks with details of any code changes
for
their tasks.
E. Enable static code analysis during the automated build.
F. Enable a check-in policy that requires a work item be associated with the check-in.
Answer: CF

Microsoft   70-498 dumps   70-498 pdf   70-498

NO.3 Your development team uses Scrum as its process framework.
You need to identify key metrics for measuring the effectiveness of any process changes.
Which three key metrics should you measure? (Each correct answer presents a complete solution.
Choose three.)
A. number of classes in the code-base
B. number of tasks added to the sprint after the sprint starts
C. number of story points delivered during the sprint
D. number of manual test cases created
E. number of bugs reported by testers
F. number of items added to the Product Backlog
Answer: BEF

Microsoft exam dumps   70-498   70-498 demo   70-498 exam prep   70-498

NO.4 You are using the Microsoft Framework (MSF) for Capability Maturity Model Integration
(CMMI) Process
Improvement 6.0 process template. You are the scrum master. You need to assign product
requirements
to an iteration.
Which three actions should you perform? (Each correct answer presents part of the solution.
Choose
three.)
A. Prioritize each of the requirements.
B. Estimate the cost of each of the requirements.
C. Create a test harness to confirm that the business requirements are understood.
D. Create a prototype to validate whether or not the requirement can be accomplished.
E. Find the dependencies among the product requirements.
Answer: ABE

Microsoft   70-498 braindump   70-498   70-498   70-498

NO.5 A development team in your company has been unsuccessful delivering software by its
deadline. You
join the team as its new scrum master. The previous scrum master did not understand the
importance of
the length of a sprint. You need to define how long the sprints should be.
Which two factors should you consider to determine sprint length.? (Each correct answer presents
part of
the solution. Choose two.)
A. The sprint length should be long enough to create a usable and potentially releasable product.
B. The iteration length should be consistent.
C. The iteration length should be flexible.
D. The iteration length should be longer than one month.
E. The iteration length should be long enough to ensure than no more than 20 percent of the total
effort is
spent performing deployment and administrative tasks.
Answer: AE

Microsoft exam dumps   70-498 pdf   70-498   70-498

NO.6 Your network environment includes a Microsoft Visual Studio Team Foundation Server (TFS)
2012
server. Your development team is using the Microsoft Framework (MSF) for Agile Software
Development
6.0 process template. You have a number of user stories logged in TFS 2012. Several user stories
have
external dependencies on an application programming interface (API) that is being developed by a
third
party. The interfaces for the API have already been agreed upon. You need to recommend how
these
external dependencies should be handled in your current sprint.
What should you do?
A. Add a resource to represent the third party and assign all the user stories that have dependencies
on
the API to this new resource.
B. Add an agreed upon amount of effort to every user story that has dependencies on the API.
C. Create mockups of the API using the agreed upon interfaces. Add user stories for integration
testing to
the backlog.
D. Move all user stories that have dependencies on the API to the next sprint.
Answer: C

Microsoft test answers   70-498   70-498   70-498   70-498

ITCertKing offer the latest 70-488 exam material and high-quality CAT-380 pdf questions & answers. Our 70-460 VCE testing engine and LOT-408 study guide can help you pass the real exam. High-quality HP2-N37 dumps training materials can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertking.com/70-498_exam.html

没有评论:

发表评论